Highlights from Meeting Regarding Patchogue-Holbrook Road Bridge

As mentioned previously, the Lake Ronkonkoma Civic Organization has received many complaints about the status of the work on the Patchogue-Holbrook Road bridge.  We arranged for a community meeting NYS Dept of Transportation to find out more information about when the project can expected to be completed.  

The meeting was held on June 27th at the Sachem Public Library.  Here are some highlights:
 
  • Approximately 50 members of the community were in attendance.
 
  • The bridge was in very bad shape, poorly maintained over the years.  The concrete platforms holding up the bridge were deteriorating. Some of the steel support beams needed repair. And the underpinning of the road surface was falling down.
 
  • The project has been affected by a series of delays mainly caused by accidents:  the bridge has been struck four times over the past two years by trucks.  These were serious accidents, one happened just before the work started, two significant hits subsequent to that, and one more recently.  The original completion data was June 2016 but that has obviously passed.  The contractor has an additional year (until June 2017) to complete the project, but has a financial incentive to be done before this winter.  No work can be completed during winter months.
 
  • The concrete road deck of the southbound lanes of the bridge should be poured in July, and once that's complete they can start the second half.  Those southbound lanes should be paved in July 2016 with the walkway and side rail shortly thereafter.  The northbound lanes may be paved before year end depending on weather.  It’s likely that the walkway alongside the northbound lands and that side rail will be built in the spring and may entail some limited lane closures but this isn’t definite.
 
  • The contractor will have to pay penalties if work isn’t fully completed by year end 2016 and it seems that the penalties get even more serious if work isn’t fully completed by mid-year 2017.
 
  • We learned that as part of the repairs, the bridge is being raised six inches on one end and 18 inches on the other end.
 
  • The DOT will review the traffic patterns around the bridge to try to address community concerns. Assemblyman Graf will communicate the plans and the civic will relay any news on this that we learn.
 
Thanks to everyone who attended!